Fullscreen Image

Add Task

  1. Tap a project tile.

  2. In Tasks, tap Add.

  3. Complete the required fields.

    • Parent Group

    • Task Name

    • Status

    • Percent Complete

    • Actual Start Date: The date the task started

    • Actual Duration: The number of days this task took. This refers to working days only. A duration of 1 means the task was finished the same day it started.

    • Original Start Date: The baseline start date

    • Projected Start Date: The start date you are aiming for

  4. Enter Comments if required.

  5. Tap Save.

  6. To upload the change, tap Update Project.